已知用塔式起重机吊运混凝土。测定塔节需时40s,运行需时50s,卸料需时60s,返回需时30s,中断20s,每次装混凝土0.55m3,机械利用系数0.90。求该塔式起重机的时间定额和产量定额。
已知用塔式起重机吊运混凝土。测定塔节需时40s,运行需时50s,卸料需时60s,返回需时30s,中断20s,每次装混凝土0.55m3,机械利用系数0.90。求该塔式起重机的时间定额和产量定额。
【正确答案】:(1)计算一次循环时间
40s+50s+60s+30s+20s=200s
(2)计算每小时循环次数
60x60/200次/h=18次/h
(3)求塔式起重机产量定额
18x0.55x8x0.9 m3/台班=71.28m3/台班
(4)求塔式起重机时间定额
1/71.28台班/m3≈0.01台班/m3