In case, within a reasonable time, the Contractor fails to carry out such instruction, the Employer shall be entitled to employ and pay other persons to carry out the same. Provided that if, in the opinion of the Engineer, the Contractor is liable to
In case, within a reasonable time, the Contractor fails to carry out such instruction, the Employer shall be entitled to employ and pay other persons to carry out the same. Provided that if, in the opinion of the Engineer, the Contractor is liable to do such work at his own cost under the Contract, all the costs in question consequent thereon or incidental thereto shall, after due consultation with the Employer and the Contractor, be determined by the Engineer, and shall be recoverable from the Contractor by the Employer.
【正确答案】:当承包人未能在合理的时间内执行这些指标,业主有权雇佣他人从事该项工作,并付给报酬。如果工程师认为该项工作按合同规定应由承包人自费进行,则在与业主和承包人协商之后,工程师应确定所有由此造成或随之产生的费用,应由业主向承包人索取。