At all times during the performance of the works, the Subcontractor shall provide the Contractor with accurate and complete information with respect to the works already performed,the works in progress, the works scheduled and the events effecting th
At all times during the performance of the works, the Subcontractor shall provide the Contractor with accurate and complete information with respect to the works already performed,the works in progress, the works scheduled and the events effecting the performance thereof and shall make available to the Contractor all relevant planning and reporting documents (daily,weekly and monthly progress reports, accident and security reports, payrolls,list of labour staff and expatriates) .
【正确答案】:在实施分包工程期间,分包商应随时向承包商提供有关已完成工程、在建工程、计划完成工程和影响施工事件方面的精确完整的资料,同时应向承包商提供所有相关的计划和报告文件(每日、每周和每月的进度报告、事故及安全报告、计算报告和劳务职员与外籍人员名单)。
【题目解析】:p210